A manufacturing plant has both safety instrumented systems (SIS) and basic process control systems (BPCS). Should they be in the same zone?
A.Only if they use the same network
B.No, SIS should be in a separate zone due to its higher security and safety requirements
C.It does not matter
D.Yes, they control the same process, a consideration that only matters when a safety instrumented system shares physical infrastructure with a basic process control system, a sharing arrangement that this question does not describe
Why B is correct
Safety instrumented systems should be in a separate zone from BPCS due to their critical safety function and higher security requirements.
Know someone studying for ISA/IEC 62443? Send them this one.
Where this fits in the ISA/IEC 62443 exam
IEC 62443: Zones, Conduits & Security Levels
Zones and conduits partitioning model, security levels (SL 1-4), target vs. achieved vs. capability security levels.
This question belongs to the "Zones, Conduits & Security Levels" domain, which makes up about 20% of the ISA/IEC 62443 exam.
CyberCertPrep gives you 20 free ISA/IEC 62443 questions per day with this same answer-and-explanation depth, plus timed exam simulations and progress tracking. No card required.
ISA/IEC 62443 and ISA/IEC are trademarks or registered trademarks of their respective owners. CyberCertPrep is an independent exam-preparation resource and is not affiliated with, authorized by, sponsored by, or endorsed by ISA/IEC or any other certification body. All study material is independently created; the certification name is used only to identify the exam this resource helps you prepare for.
A power generation company has wind farms and a central control center. How should zones be defined?