A management review output records a decision to add two analysts to the SOC. Which category of clause 9.3.3 output does this represent?
A.A decision related to resource needs and changes to the ISMS
B.A monitoring method definition
C.An audit finding
D.A base measure
Why A is correct
Clause 9.3.3 outputs include decisions related to continual improvement opportunities and any need for changes to the ISMS, which encompasses resource decisions. Authorizing additional SOC staff is a resource and change decision arising from the review.
Know someone studying for ISO 27001? Send them this one.
Where this fits in the ISO 27001 exam
Performance Evaluation
Clause 9: monitoring and measurement, internal audit, management review, KPIs and metrics
This question belongs to the "Performance Evaluation & Improvement" domain, which makes up about 15% of the ISO 27001 exam.
CyberCertPrep gives you 20 free ISO 27001 questions per day with this same answer-and-explanation depth, plus timed exam simulations and progress tracking. No card required.
ISO 27001 and ISO are trademarks or registered trademarks of their respective owners. CyberCertPrep is an independent exam-preparation resource and is not affiliated with, authorized by, sponsored by, or endorsed by ISO or any other certification body. All study material is independently created; the certification name is used only to identify the exam this resource helps you prepare for.
An organization's management review inputs include 'feedback from interested parties' but the team is unsure what qualifies. Which example...