When is risk acceptance (retention) appropriate?
A.When the risk exceeds the organization's appetite
B.Never; all risks must be treated
C.When the cost of treatment exceeds the potential loss
D.Only when mandated by law
Why C is correct
Risk acceptance is appropriate when the cost of mitigating the risk is greater than the potential impact, and the risk falls within the organization's risk appetite.
Know someone studying for ISO 27001? Send them this one.
Where this fits in the ISO 27001 exam
Iso Risk Treatment
Information security risk treatment: selecting controls, risk acceptance, and the Statement of Applicability.
This question belongs to the "Risk Assessment & Treatment" domain, which makes up about 25% of the ISO 27001 exam.
CyberCertPrep gives you 20 free ISO 27001 questions per day with this same answer-and-explanation depth, plus timed exam simulations and progress tracking. No card required.
ISO 27001 and ISO are trademarks or registered trademarks of their respective owners. CyberCertPrep is an independent exam-preparation resource and is not affiliated with, authorized by, sponsored by, or endorsed by ISO or any other certification body. All study material is independently created; the certification name is used only to identify the exam this resource helps you prepare for.
In the context of risk assessment, what is an information asset?